Nairobi Expressway: A Financial Setback – Sh 1.2 Billion Loss in Just Two Years


The Nairobi Expressway, a flagship infrastructure project aimed at easing traffic congestion in Kenya’s capital, was seen as a transformative development with immense economic potential. The highway, which stretches over 27 kilometers from the Jomo Kenyatta International Airport (JKIA) to Westlands, was envisioned as a solution to Nairobi's notorious traffic jams and a vital link between key urban areas. However, just two years after its completion, reports reveal a staggering loss of Sh 1.2 billion in revenues, casting a shadow over the financial viability of the project. This article delves into the reasons behind the Nairobi Expressway's financial challenges, the implications for its future, and the broader lessons for infrastructure projects in Kenya and beyond.




The Nairobi Expressway: Vision and Execution


Background and Development


The Nairobi Expressway project, a Public-Private Partnership (PPP) between the Kenyan government and China Road and Bridge Corporation (CRBC), was initiated to address Nairobi’s chronic traffic congestion and stimulate economic growth. With the promise of reduced travel times, improved access to key commercial hubs, and a boost to local businesses, the expressway was expected to ease transportation bottlenecks and enhance the city’s infrastructure.


The project was launched under a Build-Operate-Transfer (BOT) model, meaning the private contractor (CRBC) would fund the construction, operate the road for a specified period, and then transfer ownership to the government after the concession period. With the expressway, the Kenyan government hoped to attract more foreign investment, improve connectivity, and facilitate economic development.


Upon completion in 2022, the Nairobi Expressway became the first elevated highway in East Africa, with advanced tolling systems, modern traffic management, and enhanced road safety features. The highway was expected to generate significant revenue through toll collections, which would be used to repay the investment and maintain the road over its operational life.




Financial Performance of the Nairobi Expressway: A Disappointing Outcome


The Sh 1.2 Billion Loss


Despite high expectations, the Nairobi Expressway has faced significant financial setbacks. In its first two years of operation, the toll road reportedly made a loss of Sh 1.2 billion, falling far short of the anticipated revenue targets. The reasons for this loss are multifaceted, involving a combination of pricing issues, low traffic volume, and unforeseen challenges in the PPP framework.


1. Lower-than-Expected Traffic Volume

One of the primary factors contributing to the financial losses of the Nairobi Expressway is the lower-than-expected traffic volume. Initially, the expressway was projected to attract a daily average of 50,000 to 100,000 vehicles, but actual figures have been much lower. The road’s tolling structure, the high costs for daily commuters, and alternative routes have limited its use.



2. Expensive Toll Fees

The toll charges on the expressway are perceived by many as prohibitively high, particularly for regular users who have to travel long distances for work or business. The pricing structure has created a situation where many drivers are opting for free, alternative routes, contributing to a significant gap in revenue generation. For example, daily commuters are facing toll charges of up to Sh 300 per trip, which accumulates to a substantial monthly cost.



3. Economic Impact of the COVID-19 Pandemic

The outbreak of the COVID-19 pandemic had a profound impact on the number of vehicles on the road, especially during the initial months of the expressway's operation. With businesses closing, travel restrictions, and reduced movement across the city, traffic volume fell dramatically. The pandemic disrupted the anticipated revenue streams and delayed the full realization of the road’s potential.



4. Competition from Other Routes

The Nairobi Expressway’s route runs parallel to some of the city’s most important roads, such as Mombasa Road and Waiyaki Way, both of which are not tolled. Many commuters continue to use these routes, avoiding the expressway due to the higher costs, despite the promise of faster travel times. The existence of free alternatives has significantly reduced the number of vehicles opting for the toll road.



5. Pricing Structure and Public Perception

Public perception of the toll fees has been another challenge. While the expressway was meant to cater to those with higher incomes and businesses needing quick access to key areas, the general public feels that the tolls are unfair and disproportionate to the benefits. This sentiment has been amplified by the economic challenges faced by many Kenyans, who are struggling with inflation, high living costs, and the aftermath of the pandemic.





Implications of the Financial Losses


Challenges for the PPP Model


The financial struggles of the Nairobi Expressway raise important questions about the viability of the PPP model, especially in projects with high upfront costs and long payback periods.


1. Risk Distribution in PPPs

In the case of the Nairobi Expressway, the government and the private sector share the financial risks associated with the project. However, the low revenue generation suggests that the risk burden may fall disproportionately on the private partner (CRBC), who has already invested heavily in the construction of the road. The government may eventually have to step in with financial assistance or renegotiate the terms of the concession.



2. Impact on Future Infrastructure Projects

The financial performance of the Nairobi Expressway could have a lasting impact on the future of infrastructure projects in Kenya. If investors and stakeholders view the project as a financial failure, it could deter future investments in large-scale projects, especially those that rely on toll-based revenue models. This could make it more difficult for the government to attract funding for other much-needed infrastructure developments, such as roads, bridges, and railways.




Solutions and Potential Reforms


Reevaluating Toll Pricing and Traffic Management


To address the financial shortfall, there are several potential solutions that could help increase the expressway’s revenue while also making it more accessible to the public.


1. Revised Toll Rates:

A careful reevaluation of the toll pricing structure is necessary. The government could consider introducing differentiated toll rates based on the type of vehicle, time of day, or frequency of use. Lower rates for daily commuters or a subscription-based model could make the road more attractive to regular users, increasing traffic volume and revenue.



2. Public Awareness Campaigns:

Many potential users of the expressway may be unaware of the benefits it offers, including reduced travel times and improved safety. A targeted public awareness campaign could help shift perceptions and encourage more people to use the expressway.



3. Improved Integration with Alternative Routes:

The expressway could be better integrated with other transport networks, such as bus rapid transit (BRT) systems, which could offer affordable alternatives for commuters who may find the tolls too expensive. Additionally, improving access points and exits could help redirect traffic to the expressway, increasing usage.



4. Use of Technology to Improve Traffic Flow:

The incorporation of smart traffic management technologies could improve the flow of vehicles on the expressway, reducing congestion and making it more appealing to users. Automated toll systems and real-time updates on traffic conditions could help streamline the user experience.




Conclusion: A Cautionary Tale for Infrastructure Projects


The Nairobi Expressway’s financial struggles, marked by a Sh 1.2 billion loss in its first two years of operation, highlight the complex challenges involved in large-scale infrastructure projects, especially those relying on toll-based revenue models. While the expressway offers tangible benefits, including reduced travel times and improved urban connectivity, its high costs and competition from free routes have hindered its financial success.


Moving forward, it is crucial for the Kenyan government and private sector to reassess the pricing structure, improve public awareness, and explore ways to integrate the expressway more effectively into the city’s broader transportation system. Additionally, the lessons learned from the Nairobi Expressway’s financial setbacks can serve as a valuable guide for future infrastructure projects, both in Kenya and globally.


As the Nairobi Expressway continues its operation, the key will be finding the balance between financial sustainability and public accessibility, ensuring that the road can fulfill its potential as both an economic asset and a valuable urban transport solution.